Excelsior Correspondent
JAMMU, Oct 21: In order to carry out repairs / preventive maintenance of equipments & replacement of jumpers / droppers and other hot spots on main / reserve Bus at 220/132/33 KV Grid Station Ramban along with branch cutting of 220 KV D/C Kishenpur-Pampore Transmission line, Kishenpur-Ramban Section, the shutdown of 220/132/33 KV Grid Station Ramban, including 220 KV D/C KPTL (Kishenpur-Ramban Ckt) is being observed.
During the shutdown, the power supply to Thathar Grid, Batote Grid and Chanderkote Grid of BHEP will remain affected on October 22 from 7am to 1 pm.
Similarly, to carry out works of shifting of existing 33 KV line opposite to 220/132/33 KV Grid Station Barn, the shutdown of 33 KV Barn-Purkhoo Line emanating from 220/132/33 KV Grid Station Barn is being observed.
During the shutdown, the power supply to Purkhoo, Batera, Shamachak, Gajansoo, Marh and adjoining areas will remain affected on October 23 from 10 am to 4 pm.