Power shut down

Excelsior Correspondent

JAMMU, Sept 28: In order to carry out the R-APDRP works, the shutdown of 11 KV feeders under R-APDRP (Cluster IV) is being observed.
During the shutdown, the power supply to Lower Roop Nagar and its adjoining areas being fed from RN-5 and MU-10 feeders will remain affected on September 29 and 30 from 8 am to 12 noon and to Udheywala, Muthi, Toph, Talab Tillo, Manorma Vihar, Om Nagar, Poonch House, Kabir Colony, Colonel Colony, Bantalab, Janipur Colony, Upper Roop Nagar, Lower Roop Nagar, Subash Nagar, Muthi PHE and its adjoining areas fed from T-2, T-3, T-4, T-5, MU-4, UD-3, UD-1, UD-2, J-2, J-3, J-4, J-6, MU-2, MU-5, MU-7, MU-10, RN-1, RN-3, RN-5, BT-1, BT-3, BT-4, RN-4, SN-1, SN-3 and SN-4 from October 01 to October 15 (on alternate days) from 8 am to 12 noon.
Meanwhile, to carry out DT Erection work by M/s IRCON International Ltd under R-APDRP, the shutdown of 11 KV feeders DG-2, CB-2, D-4 and MD-3 is being observed.
During the shutdown, the power supply to Prem Nagar, Christian Colony, Upper Gummat, Lower Gummat, Company Bagh, Ambphalla, New Manda Sub Station, Manda Wild Life Sanctuary, and Ustad Mohalla will remain affected on September 30, October 1, 3, 4 and 5 from 10 am to 12 noon.
Likewise to carry out stringing work between location no 80/0 to 81/0, the shutdown of 33 KV and 11 KV lines coming under 400 KV D/C Samba-Amargarh Transmission Line is being observed.
During the shutdown, the power supply to Pamari, Changyal, Gangal, Jangbagla, Vasva, Kunah, Chameri, Balusaral, Choki Chora, Langera, Sheri, Tanda, Barradl, Nathal, Balli Gulban and its adjoining areas fed from Tanda-Choki Chora, Tanda to Balli Gulban and Balli Kalaba feeders will remain affected on September 29from 9 am to 4 pm.
Similarly, to carry out the work of laying of 11 KV HT AB Cables under R-APDRP works, 11 KV feeders TRN-1, TRN-2, TRN-3, TRN-4, TRN-6 and N-9 emanating from 33/11 KV R/Stn Trikuta Nagar will remain under shutdown.
During the shutdown, the power supply to Trikuta Nagar and its adjoining areas will remain affected on September 29 and 30 from 7 am to 12 noon respectively.