JAMMU, Oct 6: In order to carry out the erection of 11 KV D/C line under ERA at Green Belt Part, the power supply to A/D, B/D, D/C Green Belt, Hotel Asia and adjoining areas fed from RC-I feeder emanating from 33/11 KV R/Stn Railway complex will remain affected on October 8, 10 and 12, 2012 from 6 a m to 1 p m.
Meanwhile, to out preventive maintenance and replacement of damaged jumpers, droppers etc at grid station Akhnoor besides the branch cutting along the Barn-Akhnoor transmission line section, the power supply to Tanda, Jourian, Akhnoor and Ranjan fed from Grid Station Akhnoor will remain affected on October 7, 2012 from 7 a m to 2 p m.
Similarly, in order to replace the worn out jumpers and for replacing the 66 KV CT of Channi feeder alongwith the routine maintenance of 66 KV yard at 220/132/66 KV, 320 MVA Grid Station Hiranagar, the power supply to Hiranagar, Ghagwal, Dayalachak, Channi and adjoining areas will remain affected on October 7, 2012 from 7 a m to 12 noon.