Excelsior Correspondent
JAMMU, May 28: In order to carry out work of laying of HT cable on 11 KV JDA-3, 5 & 8 feeders by M/s IRCON under R-APDRP works, the 11 KVA JDA-3, 5 & 8 emanating from 33/11 KVA R/stn shall remain under shut down from May 29, 2015 to June 3, 2015 from 6 am to 10 am.
As per Executive Engineer Elect M&RE Division-II, Jammu during the shutdown period the areas affected will be Trikuta Nagar Sector 4, 5, 6, 7, 8 & 9, part of Bahu Plaza, Reserve Bank of India, Sarswati Dham and its adjoining areas.