UDHAMPUR, June 27: District Development Commissioner, Dr Piyush Singla, today convened a meeting of executing agencies and district officers of various departments to review the status of implementation of pollution abatement of river Devika and Tawi under National River Conservation Plan (NRCP), .
Detailed discussions were held on various issues which included status of execution of work on three STPs and 7 IHSPs and timely completion, vetting of design by MNIT, IEC activity for sensitization and behavioural change among the masses about the sanctity of holy River Devika and pert chart for evaluation and monitoring of the project on regular basis, status of shifting of utilities.
DDC took extensive review of pollution abatement of Rivers Devika and Tawi project and expressed anguish over slow progress of execution work under taken by concerned agencies. He asked concerned authorities to expedite the pace of work.
DDC fixed targets for the month of July and asked the concerned agencies to submit daily progress report.
DDC directed the UEED to submit all the approved design to the executing agencies and ensure work is started on all components of the project. He also asked the ACD to start IEC activity around the Devika area.
DDC expressed anguish over the working of project management consultancy (PMC) and asked PMC to monitor the work on daily basis and submit report and ensure quality and design of work is intact.