DDC Rajouri reviews developmental works, sets deadlines for completion of projects

Excelsior Correspondent

RAJOURI, Feb 13: District Development Commissioner Rajouri, Rajesh K Shavan, today convened a meeting of the concerned officers to take a comprehensive review of the physical and financial achievements by various departments and to review the functioning of various departments.
While reviewing the working of the Forest Department, the DFO informed the meeting that currently there are two schemes being implemented by the department in the district including fencing and plantation. It was given out that the work on fencing is going on and work on the plantation will start by the end of February.
To prohibit the smuggling of the minor forest products, the concerned officer said that a check post needs to be installed at Kandi.
The DDC directed the concerned officer to prepare a DPR for plantation of the medicinal plants within 20 days and also asked him to carry out an afforestation drive in the district to enhance green cover in the district. He also directed the concerned officer to initiate stern action against those found involved in illegal encroachment of the forest land as per the Forest Rights Act.
About the ICDS Department, the PO ICDS informed that the Anganwadi centres are not functional in the district due to COVID-19 pandemic and dry ration is being distributed among the beneficiaries. He also briefed the chair about the progress achieved under PMMVY and other important schemes being implemented by the Department in the district.
DDC directed the PO ICDS to make the Anganwadi Centres functional within a week’s time and also asked to devise a mechanism to ensure that the salary of the Anganwadi workers and the helpers is drawn only after a satisfactory report is received from the PRI members about their performance.
Regarding the PWD Rajouri division, the concerned Executive Engineer informed that under the District Plan, there are 20 schemes which include roads only out of which the work on 18 is at different phases of execution. He further informed that 9 projects have been taken up under State Plan.
While reviewing the status of blacktopping work, it was informed that against a target of blacktopping 61 Km road length, work on 57 km has been completed.
The DDC asked the concerned officer to ensure that the work on the projects is completed within already set deadlines and maintain the quality of the material used for the construction purpose. He also directed him to start the work on all the internal roads of the town by February 20 this year. He asked the concerned officer to identify at least ten works on which double shifts can be done to ensure the time bound completion of the work on such projects.
Reviewing the working of Jal Shakti Department in Rajouri and Nowshera divisions, the DDC asked the concerned Executive Engineers to mobilize men and machinery to complete the work on the schemes strictly as per the set timelines to provide clean drinking water supply to the masses.
The DDC also reviewed the progress under Rural Development Department schemes being implemented in the district and directed for completing the work on all the PMAY houses in the district by the end of March this year.
The DDC also reviewed the progress of the COVID19 vaccination being carried out in the district. The concerned officer informed that second phase of the vaccination drive has been started in the district to inoculate the field functionaries of different Departments including Police, Revenue, Municipality and others.