32 dead in Unchahar blast, enquiry report in a month: NTPC

NEW DELHI, Nov 3: Death toll in NTPC’s Unchahar plant accident has climbed to 32 making it the country’s worst industrial disaster in eight years, while the company today said that investigations into the mishap will be completed by an enquiry panel within a month.

The accident is the worst since the 2009 collapse of a power-plant chimney under construction at Bharat Aluminium Co.’s Korba project killing 45 people.

The NTPC Management had set up an enquiry to investigate the reasons for the accident on November 1, when a boiler at 500 MW Unit-6 blasted and caused injuries to around 80 people.

“Around 80 people were affected due to this accident. 32 succumbed to injuries and 48 are under treatment,” NTPC Chairman and Managing Director Gurdeep Singh told reporters here.

As many as 12 seriously injured persons, including two with over 80 per cent burns, were air lifted and admitted to Safdarjung and Apollo hospitals in Delhi, he said, adding that all possible measures are being taken to provide immediate relief to the families of the affected people in close coordination with the district administration.

Asked about the prima facie reasons for the blast, Singh said: “Enquiry will reveal whether it was human error, violation of safety norm or others. If I will tell you the reason then it would impose my view on the committee which will give its report in one month.”

The panel is being headed by an NPTC Executive Director SK Roy and has two general managers in it.

Terming the boiler plant blast as “the rarest kind of incident”, Singh said that people maintaining the unit were the most experienced.

NTPC followed the laid down procedure to operationalise the plant and even the commissioning of the Unit-6 was delayed by six month, he said.

The commercial date of operation was April this year as the company had achieved full load of plant (running at full capacity) in March itself, he added.

The plant was declared commercially operational on September 30, 2017.

Singh said external agencies (as per the procedure) were involved in the commissioning of the plant and NTPC has asked BHEL officials to visit the plant.

BHEL had designed, manufactured, supplied and commission the 500 MW Unit-6 at the Unchahar plant of the NTPC.

On the issue whether safety audits would be conducted on other plants of the NTPC after this accident, Singh said that it is a continuous process and the finding of the enquiry will guide us to maintain all of our plants.

Asked when can NTPC make the Unit-6 operational again, he said that it will take nearly 3-6 months to put the unit back on track. (PTI)