Excelsior Correspondent
JAMMU, Mar 10: In order to execute the work for axing dead tree behind Super Bazaar near 400 KVA Sub-Station being fed by 95 mm Sq XLPE and 95 mm Sq AB Cable on 11 KV S-8 feeder, the shutdown of 11 KV feeders is being observed.
During the shutdown, the power supply to Partap Garh Mohalla, Gali Gujron, Malhotra Mohalla, Kanak Mandi, Super Bazar and its adjoining areas fed from 11 KV S-8 feeder will remain affected on March 11 from 9 am to 2 pm.
Similarly, to carry out work for dismantling of existing LT and Guard Netting of HT Line, the power supply to Gangyal and adjoining areas being fed from 11 KV, G-2, G-6 and G-8 feeders emanating from 33/11 KV 4×10 MVA R/Stn Gangyal will remain affected on March 11 from 10 am to 3 pm.
In order to remove various hotspots of 3X50 MVA Power Transformer in the 33 KV yard alongwith replacement of 33 KV breaker of the CGL make 50 MVA power transformer, the shutdown of 220/132/33 KV Grid Station Gladni is being observed.
During the shutdown, the power supply to Gandhi Nagar, Nanak Nagar, Trikuta Nagar, Residency Road, Karan Nagar, Channi and Bathindi will remain affected on March 12 from 6.30 am to 9.30 am.