Cabinet approves Zojila tunnel for Rs 6809 cr; construction in 7 yrs

Excelsior Correspondent

JAMMU, Jan 3: The Union Cabinet today approved the construction of Asia’s longest bi-directional Zojila Pass tunnel at an estimated cost of Rs 6809 crore, which will reduce the travel time between Srinagar and Leh and make it an all-weather road. Presently, Srinagar-Leh National Highway remains closed from December to April cutting off two vital districts Leh and Kargil in Ladakh region by road from the State.
The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, today gave its go-ahead to the 14.2-km long tunnel project in Jammu and Kashmir to provide all-weather connectivity between Srinagar, Kargil and Leh.
“Zojila tunnel will be the longest bi-directional tunnel in Asia. (Its) construction period (will be) seven years because of a very difficult terrain where in some areas temperature dips to minus 45 degrees celsius. The tunnel shall be a engineering marvel as first of its kind in such a geographical area,” Road Transport and Highways Minister Nitin Gadkari said.
The project would enhance the safety of travellers crossing Zojila Pass and reduce the travel time from 3.5 hours to 15 minutes, he added.
Union Minister of State in the Prime Minister’s Office (PMO) Dr Jitendra Singh, who had been following Zojila tunnel project ever since he became the Minister, told the Excelsior that the tunnel would go a long way in improving road connectivity to Ladakh region with rest of the State and the country.
Dr Jitendra Singh extended his thanks to Prime Minister Narendra Modi and Road Transport and Highways Minister Nitin Gadkari for taking special interest in approving the project.
In a series of tweets, after the Cabinet decision, Dr Jitendra Singh said the tunnel will be constructed in seven years and it will bring about economic and socio-cultural integration of these regions.
“The project has strategic and socio-economic importance and shall be an instrument for development of economically backward districts in Jammu and Kashmir. This would lead to enormous boost in employment as local businesses get linked to national market and the beautiful region is able to receive year-round tourist traffic,’’ Dr Jitendra added.
“Defence  forces have to face hard time ensuring supplies to border posts during winters. This pass is most strategic for the entire Kargil sector which has seen intrusion and war in the past,” Gadkari said.
He said the Prime Minister will lay the foundation stone of the project and work is likely to start this year.
Zojila pass is situated at an altitude of 11,578 feet on Srinagar-Kargil-Leh National Highway which remains closed during winters (December to April) due to heavy snowfall and avalanches cutting off Leh-Ladakh region from Kashmir.
The Government has given its approval to the construction, operation and maintenance of 2-lane bi- directional Zojila Tunnel with Parallel Escape (Egress) Tunnel excluding approaches on Srinagar-Leh section connecting NH-1A at Km 95 and at Km 118 in Jammu and Kashmir on engineering, procurement and construction (EPC) mode.
The construction period of the project is seven years.
“The civil construction cost of the project is Rs 4,899.42 crore. The total capital cost of the project is Rs 6,808.69 crore. It includes the cost towards land acquisition, resettlement and rehabilitation and other pre-construction activities as well as maintenance and operation cost of tunnel for four years,” the statement said.
The project aims at construction of 14.15 km long two- lane bi-directional single tube tunnel with a parallel 14.2 km long egress tunnel excluding approaches between Baltal and Minamarg in the State.
The project will be implemented by the Ministry of Road Transport and Highways (MoRT&H) through the National Highways and Infrastructure Development Corporation Limited (NHIDCL).
The main objective of the project is to provide all whether connectivity to strategically important Leh region in Jammu and Kashmir which at the moment is limited to at best 6 months because of snow on the passes and threat of avalanches.
“This project along with other ongoing projects like 6.5 km long Z-Morh tunnel at Gagangir would ensure safe, fast and cheap connectivity between the two regions of Kashmir and Ladakh,” the statement said.
It will further increase the employment potential for the local labourers for the project activities, it added.
The Government said that on completion, it will lead to enormous boost in employment as local businesses get linked to National market and the beautiful region is able to receive round the year tourist traffic.
IL&FS Transportation last year in July had said it has emerged as the lowest bidder for Rs 4,899 crore Zojila pass tunnel in Jammu and Kashmir.
“We wish to inform that the company has emerged as the lowest bidder for the aforesaid (Zojila tunnel) project. The company had quoted an amount of Rs 4,899.42 crore to be constructed in a period of 2,555 days (7 years),” IL&FS Transportation said.
Gadkari had earlier said, “We understand the plight of the people in Leh and Ladakh region who face severe crisis during winters when they are cut off from the rest of India for six months. We are committed to undertaking the project.”
On March 1, 2016, the Transport Ministry had ordered “re-bidding” for the project, which had been awarded to IRB Infrastructure.
The decision was taken at a high-level meeting, chaired by Gadkari, after Congress leader Digvijay Singh alleged that guidelines were violated while awarding the contract.
The Ministry, however, had denied the charges.