Excelsior Correspondent
JAMMU, Jan 14: For evacuation of power from Pakal Dul, Kiru and Kwar HE Projects, CVPPL started the stringing works of transmission system, here today.
The works has been started for 400kV Double Circuit (Triple HTLS Conductor) Transmission Line from Pot Head Yard of Kiru HEP to Kishtwar Pooling Station including LILO of one Circuit of 400kV D/c (Triple HTLS Conductor) Kiru – Kishtwar line at Pot Head Yard of Kwar & Pakal Dul HE Projects.
The said transmission line shall be completed well within schedule to match the commissioning of CVPPL Projects and these stringing works shall facilitate in timely completion of above transmission lines.