DDC Poonch reviews status of developmental works

Excelsior Correspondent
POONCH, Oct 6: District Development Commissioner (DDC) Poonch undertook a comprehensive review of the works and developmental projects being executed by the PWD (R&B) Circle Poonch.
This meeting was organized in light of the recent restructuring of the PWD R&B, which also encompasses the Mechanical Department.
During the meeting, a brief PowerPoint presentation on all the developmental works and their division wise distribution was given by the SE PWD (R&B) Circle Poonch.
In a firm directive, the DC stressed the importance of adhering to the rules and regulations governing the tendering and execution processes. Contractors failing to meet timelines or initiating work punctually will face stringent action in accordance with the regulations.
The DDC directed XEns to pace up the speed of all ongoing works to achieve completion in a time bound manner.
He further asked the concerned XEns to mobilize men and machinery for the saturation of all the pending schemes within set timelines.
He also called for removing bottlenecks by taking all concerned departments onboard.
The meeting was attended by Chief Executive Officer, TDA Poonch, Superintending Engineer PW (R&B) Circle Poonch, Executive Engineer PWD (R&B) Division Poonch along-with all AEEs, Chief Medical/ Education Officer Poonch, Executive Engineer PWD (R&B) Division Surankote along-with all AEEs, Executive Engineer PWD (R&B) Division Mendhar along-with all AEEs and other concerned.