Sumbal Canal Fiasco
The CAG's findings on the Sumbal Canvas canal in Ganderbal raise multiple questions. A project meant to carry water to the fields of surrounding villages has instead delivered nothing but an empty channel, blocked by heavy debris, and a bill...
The CAG's findings on the Sumbal Canvas canal in Ganderbal raise multiple questions. A project meant to carry water to the fields of surrounding villages has instead delivered nothing but an empty channel, blocked by heavy debris, and a bill of Rs 2.24 crore. Farmers who were promised irrigation have waited more than a decade, and they are still waiting. The entire sum, a NABARD loan of Rs 2.03 crore plus the state share, was received and spent between 2011-12 and 2017-18. Yet neither administrative approval nor technical sanction was ever accorded. The work was split among as many as 58 contractors. Such fragmentation defeats coherent planning, makes monitoring difficult and invites the very laxity the audit has uncovered.
Basic planning appears to have been ignored. A gravity-fed canal was chosen for a slide-prone stretch, a decision no competent survey should have endorsed. A PMGSY road later altered the alignment over about 1,800 metres, and the absence of a flume over the Nallah meant the canal could never function as intended. A credible DPR should have covered all this. The canal has been defunct since 2014, and a fresh DPR of Rs 60.38 lakh, submitted in December 2018, was still awaiting approval as of November 2023. Worse, the audit says the joint physical verification casts doubt on the authenticity of the works reported as executed. What exists on paper does not match what exists on the ground.
Perhaps the gravest question is why nobody raised an alarm. Over several years, engineers, divisional officers and supervisors presumably signed off on payments, yet no one appears to have asked what was being built in the name of the Sumbal canal. No one has been held accountable, and the money has effectively vanished. The Department's defence is equally unconvincing. Citing records lost in the 2014 floods has become a convenient refuge, invoked whenever awkward questions arise.
Factually, NABARD loan is taxpayers' money. The CAG also found that across 13 of 20 selected I&FC projects, works were split among 276 contractors, which suggests the problem is structural rather than isolated. The Government must take the report at face value. A credible inquiry should fix responsibility, examine the reported expenditure and recover any losses. Procedural reforms, including mandatory approvals, single-contract awards where feasible and independent verification before payments, are overdue. Without such corrective action, Sumbal will not be the last canal to run dry.