Power shut down

Excelsior Correspondent
JAMMU, Mar 26:  In order to carry out the erection of 13 Mtr. ST poles for erection of new 33 KV line from Gladni to Channi, the power supply to Channi Himmat, Sainik Colony, Channi Rama, MES Sunjwan, Chowadi and their adjoining areas fed from G-6 line emanating from Grid Station Gladni will remain affected on March 27 (Sunday) from 10 am to 2 pm.
Similarly, to carry out erection, testing of 132 KV CT’s and 132 KV new Transformer Bay, the power supply to Gangyal Industrial Complex, Trikuta Nagar, Preet Nagar, Seora, Babliana, Miran Sahib and their adjoining areas fed from 50 MVA, 132/33 KV Grid Station Gangyal will remain affected on March 27 (Sunday) from 9 am to 2 pm.
Meanwhile, to carry out the work of laying of HT/LT cables on 11 KV RC-1, SA-3 and GK-1 feeders by M/S. IRCON under R-APDRP, the power supply to Railway Complex, Satwari, Greater Kailash and its adjoining areas fed from 33/11 KVS R/Stns Railway Complex, Satwari and Greater Kailash will remain affected onMarch 27 from 9 am to 5 pm.
Similarly, the power supply to Channi Himmat 3, 6, 7 and its adjoining areas fed from 11 KVA CH-3, CH-6 and CH-7 feeders emanating from 33/11 KVA R/Stns Channi Himmat, Railway Complex, Satwari and Greater Kailash will  remain affected on March 28, 30 and April 02 from 9 am to 5 pm.

LEAVE A REPLY

Please enter your comment!
Please enter your name here